Most contractors undertake the work in a similar way, but the end result
can vary enormously in quality, depending on the experience of the contractor, the quality
of brush and the ability of the brush packers.
Typically there will be preparation work required to clear the fence line prior to
fence erection. Existing fences will need to be cleared including removal of the old
posts, rails and cladding and trimming of tree limbs and shrubs. Sometimes an old
concrete base will need to be removed, sometimes it can be re-used or used as a sub-base
to the new base.
Cutting the Old Wiring
|
Clear the Fence Line
|
| Often there is considerable work in preparing
a site and even tip fees can be a significant cost factor. These costs are
additional to the quoted metre rates. Two 6 metre trailer loads of old brush, posts
and concrete and tree limbs were generated by this 50 metre long corner fence, costing $80
in tip fees and $180 in labour.
Where a brush fence is to be fitted to the top of a masonry wall or existing concrete
foundation, concrete core drilling may be required or dog leg posts may need to be
fitted. Typically core drilling contractors charge about a dollar a centimetre, or
about $30 per hole.
|
Removing the Old Base
|
and Stacking
|
| The fence depicted in this page was an old timber
posted fence in the order of 40 to 50 years old. The posts had rotted out
beneath ground level many years ago and even the timbers stubs used many years after the
fence was built to support the rotted posts, had rotted themselves. The concrete
base while substantial, had moved over the years and needed to be replaced. The old
fence panels are removed prior to being taken to the tip.
|
Stacking the Rubbish
|
Gear to the Job
|
| Considerable materials need to be brought to a
job, including posts, formwork, pins, sand metal and cement and hand tools and barrow etc.
2. Setting the Alignment & Posts
Click on images to enlarge! |
Fence Line is Cleared
|
Setting Alignment
|
| When the site has been cleared, the fence
alignment is determined and the end posts set. The balance of the post holes are then
dug 600mm deep to a stringline at 2.4 metre spacings or less. |
Hole Digging
|
Setting the Posts
|
| Click on images
to enlarge!
3. Setting the Formwork & Pouring the Base
Once all the posts, including any gate posts, have been set using hand mixed concrete,
the top line is adjusted/fine tuned to best suit the location and, the formwork is then
laid out. Setting out and getting the correct top line to suit the location and
adjoining structures is one of the most important aspects of the job, requiring skill and
experience. |
Forming
Up
|
Forming
Up
|
| The formwork is wired up and checked prior to
20/80 readymix concrete being poured. |
Pinning
the Formwork
|
Readymix is Poured
|
| Click on images
to enlarge! Reinforcing rod (Y12) is pushed into the wet concrete, the
boards are knocked/vibrated with hammers to remove entrained air and then the surface is
finished. Adelaide Brush fits steel reinforcing rod to all its bases, although there
are few other contractors past or present that do so. Due to the small 150x150mm
base cross-section, the reinforcing won't stop cracking due to tree root damage, but it
will stop the base from falling apart. |
Reinforce and Pour and
|
Finish
|
| Concrete finishing to the top surface texture is
not critical as the brush covers it, but the lines of the base edges are important to get
straight in both planes.
4. Fitting the Rails, Wiring Up and Packing
|
Fitting
Rails/Wiring
|
|
| The posts are marked ready for wiring up and the
internal 'spreader' rails are cut and fitted. The fence is then wired up in three or
four bay sections using 7 wires for an 1.8 metre fence. Click
on images to enlarge! |
Brush Packing
|
Brush Packing
|
|
|
Brush Packing
|
Brush Packing
|
| Click on images to
enlarge! |
Packing
|

|
| The brush is then packed to a high density (no
daylight) level of finish, with a top tradesman completing about two to three panels (5 to
7 metres) in a normal working day. The bottoms are cut with hand shears as the
packing progresses. |
|
|
Fitting Wire Clips
|
Pinning
|
| Wire pins (clips) are fitted through the fence at
intervals of about 350mm, clamping the brush layers tightly together. It is
important that clips are very tight and spaced no more than the above measure, to prevent
sag. |
Cutting the Bottoms
|
Cutting the
Brush Tops
|
| When all the packing is complete and post rolls
completed, the top of the fence is cut and wires fitted preparatory to the fitting of the
brush roll top.
5. Fitting the Post Rolls & Brush Roll Top (or steel capping)
Fitting Post Rolls
|
Fitting the Roll Wires
|
Click on images to enlarge! |

|
the Roll Top
|
| The roll top requires very experienced tradesmen
and the pick of the brush to get the best results. Many packers are unable to do a
good 'roll'.
6. Fitting Accessories & Finishing
|
Fitting Accessories
|
Finished Job
|
| Accessories such as letterboxes and gates are
then fitted and the job is cleaned up.
7. Cleanup & Removal of Offcuts to the Tip
Typically a 50 metre fence such as the one depicted above will generate a large volume
of offcuts, taking one man about two hours to clean up and about $40 in tip fees which is
included in the normal metre rate.
Click on images to enlarge! |
Offcuts are loaded and .....
|

.... Offloaded at the Tip
|
© Copyright 1998; Adelaide Brush, Fairview Park, South Australia 5126; Tel +61 8
82513309, Fax. +61 8 82893155, Mobile 0418 841 889.